Prototype build — data below is illustrative, not a live feed.

Stonewick Digital Infrastructure Park

Paused

Marrow Falls, Marrow County, Pennsylvania · Developer: Halden Ridge Data Partners

Approved in 2025, then paused by the developer pending a renegotiated grid interconnection agreement.

Planned capacity

320 MW

Acreage

390 ac

Investment

$1.75B

Est. jobs

65

Utility

Marrow Rural Electric

Water use

Hybrid cooling, est. 150,000 gal/day (proposed)

Next hearing

None scheduled

Status

Paused

Updates

Chronological record of reported developments on this project.

  1. November 14, 2025

    County approves Stonewick site plan

    Status change: Permitting → Approved

    Marrow County approved the site plan for a 320 MW campus, one of the largest proposed in the county to date.

  2. May 28, 2026

    Developer files amended interconnection request

    Halden Ridge Data Partners submitted a revised interconnection request to the regional grid operator after the original filing was returned for additional study.

  3. June 1, 2026

    Construction paused pending grid interconnection talks

    Status change: Approved → Paused

    The developer confirmed site work has paused while it renegotiates interconnection terms, with no revised construction start date announced.

Sources

Underlying citations for this project's record.